Park Ave.

 

What's Happening on Park Avenue?
 
Drivers, bicyclists and pedestrians on Park Avenue may have encountered construction along Park Ave. and in the road Right of Way.  No, the road is not being repaved.  PAWSD has begun work upgrading a sewer line. 

PAWSD will install a lift station and an 8” forced main which will connect to an existing lift station.  This will redirect wastewater flows in order to redistribute the load on the existing system.

Traffic delays and detours will be at a minimum since most of the work will be in the Right of Way.  The work is expected to take a total of thirty days; work began the last week of August. 
 
As of September 30, all work has been completed except for the installation of the lift station.

Park Ave and ROW stakes
 Stakes along the golf course indicate future sewer line work.

 